Turnkey construction TA for Atlas Development
Customer:
Customer: Atlas Development Ltd.
Object: Electricity supply to the Capital Park residential complex in Yekaterinburg
Purpose and objectives:
Goal: Construction and commissioning of a TP built into the parking lot. 0.4kV distribution networks.
Tasks: In a short period of time in the cramped conditions of the underground parking lot to install the transformer substation 4x630 kVA, perform start-up and adjustment works.
Terms of implementation:
2023 гDescription of the project:
In the central part of Yekaterinburg, the largest developer was building the elite Residential Complex “Capital Park”, for its power supply in the limited conditions of the building in the parking lot were built substations with the use of small-sized electrical equipment.
Implemented design solution:
Within the framework of the construction RME 6 cells, IDR-T 630kVa 4pcs cast-insulated transformers, 0.4 kV switchgear, busbar lines over 100 meters were installed. Start-up and adjustment works were carried out, the object was handed over to the Customer within the terms agreed by the contract. Delivery of equipment and works were carried out in a short period of time, the works were carried out under the conditions of limited space of the parking lot. The Customer's choice in our favor was due to the availability of some electrical equipment in our warehouses and the possibility of supplying RME cells with better terms than our competitors. Based on the results of the works, the Customer chose us for the next scope of works.